Chen Jiawei, Dan Zeyi, Lin Hong. THE DESIGN OF CRANE BEAM SYSTEM WITH COLUMN REMOVED IN A LARGE STEEL FACTORY[J]. INDUSTRIAL CONSTRUCTION, 2013, 43(2): 134-137. doi: 10.13204/j.gyjz201302027
Citation: Chen Jiawei, Dan Zeyi, Lin Hong. THE DESIGN OF CRANE BEAM SYSTEM WITH COLUMN REMOVED IN A LARGE STEEL FACTORY[J]. INDUSTRIAL CONSTRUCTION, 2013, 43(2): 134-137. doi: 10.13204/j.gyjz201302027

THE DESIGN OF CRANE BEAM SYSTEM WITH COLUMN REMOVED IN A LARGE STEEL FACTORY

doi: 10.13204/j.gyjz201302027
  • Received Date: 2012-08-20
  • Publish Date: 2013-02-20
  • The large cantilever crane girder system was formed after removing the corner column in a large wire bar workshop.The load of roof was carried by the roof limb truss and the load of crane was carried by the continuous cantilever crane beam.At the same time,through the design of detail treatment,the system spatial entirety and structural deformation coordination were ensured.
  • loading
  • [2] 刘昌杞,张利群,付丰博.国外桥式吊车分级和荷载规定的动向[J].工业建筑,1988,18(11):12-129.
    崔佳,魏明钟,赵熙元,等.钢结构设计规范理解与应用[M].北京:中国建筑工业出版社,2004:346.
    [3] 张利群,付丰博.大型吊车梁的制作[J].工业建筑,2005,35(增刊):783-789.
    [4] 薄占秀.冶金工业厂房设计的若干问题[J].工业建筑,1993,23(8):19-25.
    [5] 朱国华.钢吊车梁系统空间作用的分析和计算(上)[J].工业建筑,1980,10(4):48-52.
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Article Metrics

    Article views (51) PDF downloads(75) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return