Yang Baozhu, Shao Qiang, Ding Kesheng, Zhang Shuchao, Xu Changling. STUDY ON HOISTING PROCESS OF SUPER DEEP AND LARGE REINFORCEMENT CAGE FOR DIAPHRAGM WALL[J]. INDUSTRIAL CONSTRUCTION, 2013, 43(7): 101-104. doi: 10.13204/j.gyjz201307023
Citation:
Yang Baozhu, Shao Qiang, Ding Kesheng, Zhang Shuchao, Xu Changling. STUDY ON HOISTING PROCESS OF SUPER DEEP AND LARGE REINFORCEMENT CAGE FOR DIAPHRAGM WALL[J]. INDUSTRIAL CONSTRUCTION, 2013, 43(7): 101-104. doi: 10.13204/j.gyjz201307023
Yang Baozhu, Shao Qiang, Ding Kesheng, Zhang Shuchao, Xu Changling. STUDY ON HOISTING PROCESS OF SUPER DEEP AND LARGE REINFORCEMENT CAGE FOR DIAPHRAGM WALL[J]. INDUSTRIAL CONSTRUCTION, 2013, 43(7): 101-104. doi: 10.13204/j.gyjz201307023
Citation:
Yang Baozhu, Shao Qiang, Ding Kesheng, Zhang Shuchao, Xu Changling. STUDY ON HOISTING PROCESS OF SUPER DEEP AND LARGE REINFORCEMENT CAGE FOR DIAPHRAGM WALL[J]. INDUSTRIAL CONSTRUCTION, 2013, 43(7): 101-104. doi: 10.13204/j.gyjz201307023
Based on Z1-section of Tianjin cultural centre transport hub, the model of super deep reinforcement cage for diaphragm wall was built by the ABAQUS finite element analysis software and site monitoring method.It was mainly studied one-time hoisting process of 1 shape 55 m reinforcement cage in different conditions.ABAQUS could predict the construction preparation and construction process, and also provide hoisting parameters for the actual hoisting procedure.The predicted results could analyze potential problems and risks of the actual hoisting process.