Yang Min, Gao Gonglue. TEST OF FOUNDATION REINFORCEMENT OF OPERATIONAL SUBSTATION BY DEVELOPING SMALL-SCALE PILE DRIVER[J]. INDUSTRIAL CONSTRUCTION, 2010, 40(7): 118-122. doi: 10.13204/j.gyjz201007029
Citation: Yang Min, Gao Gonglue. TEST OF FOUNDATION REINFORCEMENT OF OPERATIONAL SUBSTATION BY DEVELOPING SMALL-SCALE PILE DRIVER[J]. INDUSTRIAL CONSTRUCTION, 2010, 40(7): 118-122. doi: 10.13204/j.gyjz201007029

TEST OF FOUNDATION REINFORCEMENT OF OPERATIONAL SUBSTATION BY DEVELOPING SMALL-SCALE PILE DRIVER

doi: 10.13204/j.gyjz201007029
  • Received Date: 2009-04-13
  • Publish Date: 2010-07-20
  • The settlement of the foundation on the soft ground would affect the normal operation and safety of the substation. The existing reinforcing methods and machinery can't work in the high-voltage fields. For a 220kV substation on the sea sediment foundation in a city along the coast, Jiangsu Province, China, the settlement should be controlled at a 2.2m high security restrictions with the requirement of the original operation of the substation. A small-scale pile-driver was developed, and reinforcement tests were carried out. The results show that the small-scale pile driver can work well for running substation, which is a breakthrough of the reinforcement of substation foundation at the restricted space. The micro-steel pipe pile can effectively prevent the settlement of independent foundation.The technology of prestressing on the pile top, soldering after withstand, can improve reinforcement effect.
  • loading
  • [2] 罗伶. 某变电站主变压器地基不均匀沉降分析与处理[J]. 电力勘测设计,2004(4) : 28-31.
    曾志强. 变电站工程中因软基引起的结构沉降问题研究[J].建材技术与应用,2008(8) : 33-34.
    [3] 祝红山,贡伟. 某变电站设备支架的地基处理[J]. 能源技术与管理,2007(3) : 104-105.
    [4] 戴洪军,郭纪中,马骥. 变电所支架差异沉降及防治对策[J].电力勘测设计,2005(2) :16-20.
    [5] 陆瑞明,刘洪波,刘平. 变电站构架基础加固纠偏工程实践[J]. 建筑技术,2004(6) :49-50.
    [6] 陈开荣. 微型钢管桩在莆田500 kV 变电站构架基础加固中的应用[J]. 福建建筑,2002(S1) :33-34.
    [7] 杨敏. 微型钢管桩施加预应力加固沉降基础的试验[J]. 建筑技术,2008(6) :465-466.
    [8] 魏焕卫. 采用顶升法和微型桩的纠偏加固设计施工[J]. 建筑技术,2006(6) :455-457.
    [9] 史佩栋. 实用桩基工程手册[M]. 北京:中国建筑工业出版社,1999.
    [10] 金问鲁. 地基基础实用设计施工手册[M]. 北京:中国建筑工业出版社,1995.
    [11] 王天稳. 土木工程结构试验[M]. 武汉:武汉理工大学出版社,2006.
    [12] 张永青,吴坚强,李今保,等. 某厂房柱纠偏加固技术[J]. 工业建筑,2008,38(2) :106-108.
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Article Metrics

    Article views (56) PDF downloads(93) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return