An Guanfeng, Gao Junyue. ANALYSIS OF DEEP EXCAVATION RETAINING DESIGN AND ITS CONSTRUCTION MONITORING FOR THE WUSHAN METRO STATION[J]. INDUSTRIAL CONSTRUCTION, 2005, 35(12): 61-66. doi: 10.13204/j.gyjz200512017
Citation:
An Guanfeng, Gao Junyue. ANALYSIS OF DEEP EXCAVATION RETAINING DESIGN AND ITS CONSTRUCTION MONITORING FOR THE WUSHAN METRO STATION[J]. INDUSTRIAL CONSTRUCTION, 2005, 35(12): 61-66. doi: 10.13204/j.gyjz200512017
An Guanfeng, Gao Junyue. ANALYSIS OF DEEP EXCAVATION RETAINING DESIGN AND ITS CONSTRUCTION MONITORING FOR THE WUSHAN METRO STATION[J]. INDUSTRIAL CONSTRUCTION, 2005, 35(12): 61-66. doi: 10.13204/j.gyjz200512017
Citation:
An Guanfeng, Gao Junyue. ANALYSIS OF DEEP EXCAVATION RETAINING DESIGN AND ITS CONSTRUCTION MONITORING FOR THE WUSHAN METRO STATION[J]. INDUSTRIAL CONSTRUCTION, 2005, 35(12): 61-66. doi: 10.13204/j.gyjz200512017
The deep excavation of Wushan Metro Station is near multi-story apartments with natural foundation and Yuezhou Road with heavy traffic.Considering the high jetting mixing pile for water-proofing of foundation, the foundation with 17.7m depth is designed for using diaphragm wall with multi-story support.The deep excavation monitoring is done during its construction in detail, and a lot of monitoring data are obtained while the construction lessons are given.The experience is worth considering in similar cases.