Yang Zhongbao, Zou Daoqin, . THE SITE TEST OF SUPER-LENGTH CONCRETE STRUCTURE[J]. INDUSTRIAL CONSTRUCTION, 2005, 35(8): 64-66,74. doi: 10.13204/j.gyjz200508016
Citation:
Yang Zhongbao, Zou Daoqin, . THE SITE TEST OF SUPER-LENGTH CONCRETE STRUCTURE[J]. INDUSTRIAL CONSTRUCTION, 2005, 35(8): 64-66,74. doi: 10.13204/j.gyjz200508016
Yang Zhongbao, Zou Daoqin, . THE SITE TEST OF SUPER-LENGTH CONCRETE STRUCTURE[J]. INDUSTRIAL CONSTRUCTION, 2005, 35(8): 64-66,74. doi: 10.13204/j.gyjz200508016
Citation:
Yang Zhongbao, Zou Daoqin, . THE SITE TEST OF SUPER-LENGTH CONCRETE STRUCTURE[J]. INDUSTRIAL CONSTRUCTION, 2005, 35(8): 64-66,74. doi: 10.13204/j.gyjz200508016
The site test of super -length concrete structure is introduced in detail.The results show that it is effectual to take some measures,such as pre -stressing,constructing the later poured bands,to control thermal deformation and insure the security of structure,the super -length design is achieved,and it may be a reference for similar projects.