Analysis on Dewatering Tests at Deep Excavation Sites of Soft Soil Areas in Aquifer-Connected Conditions
-
摘要: 地铁车站基坑施工建设过程中,基坑土方开挖需要干作业面,基坑降水过程必不可少。在降水井施工完成后,须进行预降水试验来检验能否满足基坑开挖条件及止水帷幕截水效果。但个别建设单位未对此产生足够重视,往往因降水试验所需时间、经济成本,而忽略或放弃筹备进行降水试验,给工程施工埋下一定的安全隐患。基于天津地铁某车站的基坑降水试验数据进行研究分析,发现由于基坑降水井成井施工质量未严格达到要求,造成含水层间相互联通,基坑降水难以满足开挖设计要求。随后,通过采用双液浆注浆加固处理措施封堵隔水层确保其隔水效果,满足基坑降水设计要求的同时,防止了因基坑内疏干降水引发基坑外水位大幅变化对周边环境产生的影响。Abstract: During foundation excavation of metro stations, the dry working surface was needed, and dewatering in site is essential. After construction of dewatering wells, the pre-dewatering must be performed to check whether it can meet the excavation condition and the water interception effect for curtain of cutting-off water. However, some construction enterprises do not attach importance to the issues, and often ignore or abandon the preparation for the dewatering test due to considering of time and economic costs, laying a certain potential safety hazard for project construction. Based on data analysis on the dewatering test at the deep excavation site of a metro station in Tianjin, it was found that because the construction quality of dewatering wells did not strictly meet the design requirements, the aquifers were interconnected, and led to the foundation dewatering not to meet the design requirements. Subsequently, a grouting reinforcement measure, which alternately injected water glass and calcium chloride solutions into water-resisting layer, was adopted to block water leakage and ensure its water resisting effect and meet the design requirements of dewatering, and simultaneously prevent the impacts of the significant change in groundwater levels caused by dewatering for deep excavation on the surrounding environment.
-
Key words:
- dewatering for excavation /
- drawdown /
- diaphragm wall /
- connected aquifer
-
[1] 郑刚.软土地区基坑工程变形控制方法及工程应用[J].岩土工程学报,2022,44(1):1-36,201. [2] 张兴.抽水试验及数值模拟在基坑工程中的应用[J].岩土工程技术,2021,35(5):306-311. [3] 丁洲祥, 龚晓南, 俞建霖, 等. 止水帷幕对基坑环境效应影响的有限元分析[J]. 岩土力学,2005, 26 (增刊1): 146-150. [4] 施成华, 彭立敏. 基坑开挖及降水引起的地表沉降预测[J]. 土木工程学报, 2006(5): 117-121. [5] 黄显贵,陈梁,刘御刚,等.基坑降水引起的地基附加应力及沉降简化计算[J]. 地下空间与工程学报, 2017, 13(3): 746-752. [6] 孙文娟, 沈水龙, 李耀良, 等. 基坑开挖前降水引起的地面沉降的工程实例分析[J]. 岩土工程学报, 2008 (增刊1): 314-318. [7] 哈达, 朱敢平, 李竹, 等. 天津市承压含水层条件下地下连续墙深度优化[J]. 地下空间与工程学报, 2018,14(2):490-499. [8] 曾超峰. 工程降水引起基坑及土体变形机理、规律及控制策略研究[D]. 天津:天津大学,2014. [9] 中国铁路设计集团有限公司.天津地铁7号线一期工程详细勘察:岩土工程勘察报告[R].天津:中国铁路设计集团有限公司,2018. [10] 张雪婵, 张杰, 龚晓南, 等. 典型城市承压含水层区域性特性[J]. 浙江大学学报(工学版), 2010(10): 1998-2004.
点击查看大图
计量
- 文章访问数: 24
- HTML全文浏览量: 4
- PDF下载量: 2
- 被引次数: 0