CONTRAST TESTS IN SITU OF CEMENT-SOIL WALLS BY TRD OR SMC IN THE FOUNDATION EXCAVATION OF LARGE PUBLIC BUILDINGS AND THEIR JOINT FACILITIES FOR THE CENTRAL GREEN IN BEIJING
-
摘要: 针对北京城市副中心的标志性建筑及重点配套项目基坑周边有保护历史遗迹、国家大剧院台湖舞美艺术中心剧场下穿通道及地铁线路的情况,考虑到场地地下水位高、开挖工程量大、槽底标高变化大、工程地质和水文地质条件复杂等因素,在北京地区首次采用了渠式切割深层搅拌地下水泥土连续墙工法(TRD工法)施做止水帷幕。通过对深层铣削搅拌工法(SMC工法)止水帷幕与TRD工法止水帷幕的比较表明:TRD工法水泥土搅拌墙接缝处和转角处垂直度控制较好,止水效果能够达到预期,SMC水泥土搅拌墙接缝处和转角处控制垂直度仍待进一步研究和改进。
-
关键词:
- 城市副中心 /
- 深基坑 /
- 渠式切割深层搅拌地下水泥土连续墙工法 /
- 深层铣削搅拌工法
Abstract: In the light of many monuments and metro lines around the excavated foundation of the large public landmark buildings and their joint facilities for the Central Green in Beijing Municipal Administrative Center,the underground pedestrian passage of the Grand Theatre for Beijing Municipal Administrative Center passing below it,as well as in considerations of complex engineering geology and hydrogeology and the complexity of construction,the cement-soil walls by the trench cutting remixing deep wall method (TRD) were proposed to be adopted in Beijing first to control groundwater of the project. Comparisons of sealing effects for the cement-soil walls by TRD and the soil-mixing with cutters (SMC) showed curtains by TRD had better performances of isolating groundwater than that by SMC. The construction processes of SMC needed to be improved further.-
Key words:
- municipal administrative center /
- deep excavation /
- TRD /
- SMC
-
[1] 北京市勘察设计研究院.城市绿心三大建勘察报告[R].北京:北京市勘察设计研究院,2020. [2] 北京市勘察设计研究院.城市绿心共享设施勘察报告[R].北京:北京市勘察设计研究院,2020. [3] 中华人民共和国住房和城乡建设部.建筑地基检测技术规范:JGJ 340-2015[S]. 北京:中国建筑工业出版社,2015. [4] 中华人民共和国住房和城乡建设部.城市工程地球物理探测标准:CJJ/T 7-2017[S].北京:中国建筑工业出版社,2017.
点击查看大图
计量
- 文章访问数: 64
- HTML全文浏览量: 7
- PDF下载量: 2
- 被引次数: 0