大跨度深基坑满堂支架施工技术研究
doi: 10.13204/j.gyjz201508024
RESEARCH ON FULL FRAMING CONSTRUCTION OF LARGE-SPAN DEEP EXCAVATIONS
-
摘要: 针对大跨度深基坑工程中换撑方案工期长、成本高的弊端,提出满堂支架体系取代换撑的优化方案。采用MIDAS GTS 4.0和SAP 2000有限元软件,对南京青奥轴线J2区段大跨度基坑工程分别进行换撑和满堂支架方案施工过程数值模拟,分析两种施工方案在地下连续墙侧向位移、基坑周边地表沉降、地下连续墙的受力、钢支撑轴力等方面的差异,其中重点分析了满堂支架方案对主体结构受力和满堂支架体系受力的影响。分析结果表明:采用满堂支架方案时,支护结构的变形、受力,主体结构的受力及满堂支架体系的受力均满足要求,大跨度深基坑工程采用满堂支架方案替代换撑方案进行施工是可行的。Abstract: To solve the problem of long duration and high cost of the changing-support scheme of large-span deep excavations,a new optimization method of replacing the scheme by full framing system was proposed. The finite element software MIDAS GTS 4. 0 and the finite element software SAP 2000 were respectively adopted to simulate whole construction processes of the two schemes of the large-span excavation pit project of axis J2 section of Nanjing Youth Olympics. The differences of these two schemes on side displacement of underground diaphragm walls, sedimentation of peripheral ground surface around the excavation,stress of underground diaphragm walls and axis forces of steel supports were analyzed, and the influence of the full framing scheme on the stress of main structure and full framing system was the focus of the analysis. Analysis results indicated that the deformation of supporting structure and the forces of supporting structure,main structure and full support system could meet safety requirements, so it was theoretically feasible to adopt the full framing construction scheme in this excavation project instead of the changing-support construction scheme.
-
Key words:
- excavation project /
- construction scheme /
- full framing /
- finite element analysis /
- feasibility
点击查看大图
计量
- 文章访问数: 168
- HTML全文浏览量: 3
- PDF下载量: 186
- 被引次数: 0