宁波财富中心弧形钢管混凝土柱施工技术研究
doi: 10.13204/j.gyjz201505023
STUDY OF CONSTRUCTION TECHNOLOGY OF ARC CONCRETE FILLED STEEL TUBULAR COLUMN FOR NINGBO FORTUNE CENTER PROJECT
-
摘要: 针对宁波财富中心弧形钢管混凝土柱施工中存在的对接定位安装、柱内混凝土密实度保证等技术难题,分别采用套模技术、钢管柱局部构造改变措施以及混凝土浇筑方法细化调整等综合技术,结合现场模型试验、数值分析以及超声波实体检测等方法,验证该套技术在该工程中实施的成功性,并在后续同类工程中推广运用。Abstract: Considering the technical problems such as butt joint installation and concrete compactness assurance etc in the construction of arc concrete filled steel tubular columns for Ningbo Fortune Center project,the cover mould technology,local structural changing measures for the columns and adjustment of concrete pouring method were used respectively,combined with the model test,numerical analysis and ultrasonic test method,the successfulness of this set of techniques for the project was verified,which was also applied in the subsequent similar projects.
-
Key words:
- super high-rise /
- concrete filled steel tubular column /
- arc /
- butt joint installation /
- compactness /
- countermeasure
点击查看大图
计量
- 文章访问数: 164
- HTML全文浏览量: 8
- PDF下载量: 90
- 被引次数: 0