SEISMIC REINFORCEMENT DESIGN AND CONSTRUCTION OF THE IN-PATIENT BUILDING OF A HOSPITAL
-
摘要: 某医院住院部为3层砖混结构,建于1976年,乙类建筑。由于地基浸水不均匀下沉,上部墙体开裂,且原结构抗震构造措施设置不到位,抗震性能低。针对建筑物的现状,采用静压桩、增设混凝土构造柱、圈梁等措施,稳定结构基础,并加强对上部结构的约束,使建筑整体性、抗震性显著提高,取得良好的抗震加固效果,保证在后续使用年限20年内结构的安全使用。Abstract: The in-patient building of a hospital is a structure with three layers of brick and concrete, built in 1976, class B building.There are cracks on the upper wall by the uneven subsidence due to foundation flooding, and the seismic design of the original structure was not fully realized, the seismic capacity is low.According to the status of the building the static pressing pile was used, concrete structural columns and beam were added to stabilize the foundation of structure, and strengthen the constraints of the upper structure, so as to raise its integrity and seismic ability obviously, and a good seismic reinforcement effect was got to guarantee the safe use of the structure within its follow-up life of 20 years.
-
Key words:
- multi-storey masonry /
- seismic strengthening /
- static pressing pile /
- structural column
-
JGJ 1232003既有建筑地基基础加固技术规范[S]. [2] GB 500112001建筑抗震设计规范[S]. [3] GB 502395建筑抗震鉴定标准[S]. [4] GB 50112010建筑抗震设计规范[S]. [5] JGJ 1162009建筑抗震加固技术规程[S]. [6] 03 SG 61砖混结构加固与修复[S]. [7] GB 500252004湿陷性黄土地区建筑规范[S]. [8] JGJ 942008建筑桩基技术规范[S]. [9] 陈大川,李华辉.汶川地震后某中学综合楼抗震鉴定与加固设计[J].工业建筑,2009,39(8):4-7. [10] 王玉玲,肖绪文,殷惠君,等.既有建筑结构加固改造技术手册[M].北京:中国建筑工业出版社,2010. [11] 吕西林.建筑结构加固设计[M].北京:科学出版社,2001.
点击查看大图
计量
- 文章访问数: 105
- HTML全文浏览量: 3
- PDF下载量: 86
- 被引次数: 0