REINFORCEMENT DESIGN OF THE DISEASE PILE FOUNDATION OF EXISTING BRIDGE IN KARST AREA AND NUMERICAL ANALYSIS
-
摘要: 某既有线桥梁在上部荷载长期作用下,桥墩产生沉降和倾斜,危及行车安全。勘察表明,该桥墩基础下分布有溶洞。基于突变理论,根据岩溶区桩下卧溶洞顶板失稳破坏条件,确定了位于溶洞顶部原桩的承载力;在此基础上,针对岩溶分布特征和地基承载特性,采用增补桩基-扩大承台主动加固法对其进行加固,通过理论计算确定合理桩长;同时,采用数值模拟软件,分析了桥墩基础加固前后的稳定性,以及增补桩基桩长与桥墩基础沉降和倾斜的关系。结果表明:数值计算结果与理论计算结果吻合,原桥墩基础承载力不满足设计要求,增补桩的合理长度为14.5 m,已穿透溶洞,此时承台中心沉降为6.9 mm,纵桥向承台最大沉降差为0.89 mm。Abstract: The settlement and inclination of the pier of existing railway bridge is caused by the upper long-term load, which has been affected the running safety. Geological exploration found that a large karst cave is located under thebridge pier foundation. Based on the catastrophe theory, according to the instability conditions of cave roofs thebearing capacity of the original piles was calculated. On this basis, consolidation strengthening was required for thefoundation by using the method of adding piles and enlarging bearing platform, according to the distribution of karstcave and the geological characteristics. And the proper length of adding piles was provided by theoretical calculation.What is more, the relationship between the length of adding piles and the settlement and inclination of the pier wasanalyzed, based on the numerical simulation software. The results showed that the numerical calculation resultsagreed with those of theoretical calculation. The bearing capacity of the original bridge pier foundation could not meetthe design requirements. The proper length of adding piles was 1 4. 5 m. The settlement and the maximum settlementdifference in lognitudinal direction of the bearing platform with the proper length of adding piles was 6. 9 mm and0. 89 mm respectively under the upper loads.
-
Key words:
- pile foundation /
- karst cave /
- disease /
- reinforcement design /
- numerical analysis
-
[2] 郭建通,刘建焱,郭辉,等.体外预应力技术在桥梁加固中的应用[J].工业建筑,2002,32(9):69-71. 贺玉龙,杨立中,郭永春.南昆线西街口-罗平段病害及防治建议[J].铁道建筑,2002(1):9-11. [3] 陈飞,黄晓琴.注浆技术在岩溶地层钻孔灌注桩中的应用[J].工业建筑,2008,38(增刊):891-894. [4] 肖巍兵,徐德新,陈跃庆,等.基于耐久性等级评定桥梁加固前与加固后的剩余使用寿命探讨[J].工业建筑,2009,39(5):84-88. [5] 陈红梅.钢筋混凝土桥梁病害分析及其维修加固[D].大连:大连理工大学,2011. [6] 赵明华,蒋冲,曹文贵.岩溶区嵌岩桩承载力及其下伏溶洞顶板安全厚度的研究[J].岩土工程学报,2007,29(11):1618-1622. [7] 双德斯P T.突变理论入门[M].凌复华,译.上海:上海科学技术文献出版社,1983. [8] Thompson J M T,Shamrock P A.Hyperbolic Umbilici Catastrophein Crystal Fracture[J].Nature,1976(26):598-599. [9] Carpentaria Alberto,Catastrophe A.Theory Approach to FractureMechanics[J].Int J Frac,1990(44):57-69. [10] TB10002.12005铁路桥涵设计基本规范[S]. [11] GB500092001建筑结构荷载规范[S]. [12] 黎斌,范秋雁,秦凤荣.岩溶地区溶洞顶板稳定性分析[J].岩石力学与工程学报,2002,21(4):532-536.
点击查看大图
计量
- 文章访问数: 117
- HTML全文浏览量: 6
- PDF下载量: 69
- 被引次数: 0