MONITORING OF THE OPEN-CUT SECTION OF A CABLE TUNNEL IN GUANGZHOU
-
摘要: 结合广州220 kV厚德变电站明挖段电缆隧道施工安全监测实例,系统地介绍钢板桩加钢支撑支护体系中施工安全监测设计、监测仪器设备的安放、隧道明挖法施工过程的实时监测频率、监测警戒值确定及监测报告等内容。并介绍一种新的监测方案在特殊施工场地的应用,根据现场实时监测数据,特别是异常数据的分析及安全预测,针对其结果采取相应的处理措施,避免了工程事故的发生,确保了施工现场和周围环境的安全。Abstract: Combined with the monitoring example of the open-cut section of a cable tunnel for Houde Substation in Guangzhou,the monitoring safety design and instrument layout were introduced in the system of steel sheet pile and steel struts structure.The monitoring frequency,alertness values and reports etc were presented.According to the analysis and forecast of monitoring data especially the unusual ones,monitoring result was researched to adopt countermeasures,and safety precautions were adopted in time,hence the safety of the field and environment could be ensured.
-
Key words:
- tunnel engineering /
- open-cut methods /
- steel sheet pile /
- monitoring
-
GJB 02-1998.广州基坑支护技术规定[S]. JGJ/T 8-1997.建筑变形测量规程[S]. 马健. 超大深基坑支护方案设计及施工监测[J].工业建筑,2010,(09):97-100. GB 50007-2002.建筑地基基础设计规范[S]. 陈忠汉,黄书秩,程丽萍. 深基坑工程[M].北京:机械工业出版社,1999. 潘泓,曹洪. 广州猎德大桥钢板桩围堰的设计与监测[J].岩石力学与工程学报,2009,(11):2242-2248. 骆冠勇,曹洪,潘泓. 新光大桥桥墩钢板桩围堰的优化设计与监测[J].华南理工大学学报(自然科学版),2006,(02):124-129.
点击查看大图
计量
- 文章访问数: 100
- HTML全文浏览量: 6
- PDF下载量: 73
- 被引次数: 0