DEFORMATION ANALYSIS AND REINFORCEMENT APPROACH OF YUANYANGHUI TUNNEL DURING EXCAVATION
-
摘要: 山平高速公路鸳鸯会隧道左线进洞施工中,隧道顶部和邻近坡体产生了较大变形,现场监测发现隧道最大沉降达34 cm。依据对该隧道及邻近坡体现场监测数据,应用相关理论,分析探讨洞口开挖引起隧道及仰坡不利变形的诱因,并根据监测分析结果提出控制措施。最后应用有限元方法模拟了所提出控制措施下隧道进洞开挖的过程,结果表明所提出控制措施是合理的。Abstract: Large deformation on the tunnel top and adjacent slope occurred during the face excavation construction of left line of Yuanyanghui tunnel on Shanping express highway, with maximal displacement of 34 cm monitored on site.Based on the analysis of tunnel construction process, site monitoring was carried out to the tunnel and adjacent slope, relevant theory and method were applied to investigate the inducement of its unfavorable deformation caused by excavation of tunnel opening, and control measures were also proposed according to monitoring analysis results.The face excavation construction under the control measures was analyzed by numeral simulation, it turned out to be reasonable.
-
Key words:
- loess tunnel /
- construction of tunnel entrance /
- deformation /
- control measures
-
吉武军.黄土隧道工程问题调查分析[J].岩土力学,2009,30(增刊2):387-391. [2] TB 101212007铁路隧道监控量测技术规程[S]. [3] 姜德义.边坡稳定性分析与滑坡防治[M].重庆:重庆大学出版社,2005. [4] 乔春生,管振祥,腾文彦.饱和黄土隧道变形规律研究[J].岩土力学,2003(24):225-230. [5] JTG D702004公路隧道设计规范[S]. [6] 韩桂武,刘斌,范鹤.浅埋黄土隧道衬砌结构受力分析[J].岩石力学与工程学报,2007,26(增刊1):3250-3256. [7] 徐林生.大断面高速公路隧道复合式衬砌结构受力监测分析[J].重庆交通大学学报:自然科学版,2009,28(3):528-530. [8] TB 100032005铁路隧道设计规范[S].
点击查看大图
计量
- 文章访问数: 66
- HTML全文浏览量: 5
- PDF下载量: 107
- 被引次数: 0