摘要: 通过不同隧道埋深、支护压力和掘进速度的盾构隧道施工地表沉降的大型物理模型试验,总结不同条件下的地表沉降规律,分析土压力的变化特性,归纳不同条件下的地表沉降曲线;探讨隧道埋深、支护压力和掘进速度对地表沉降值的影响,推导地表横断面沉降槽计算的经验公式。结果表明:随着隧道埋深增加,地表沉降值减小,地表横向沉降槽影响范围加宽;地表最终沉降值随支护超压比增加而增大;掘进速度变化对地表沉降的影响程度较小;施工扰动损伤围岩对地表沉降值有较大影响。Abstract: The influence of cover height,face supporting pressure and penetration rate on shield tunneling-induced ground surface settlement was studied with three-dimensinal physical model test.The mechanism of shield tunneling-induced ground surface settlement was analyzed,the ground settlement curves in different conditions were obtained,the influence of cover depth,face supporting pressure and penetration rate of shield tunnel on the surface settlement were discussed,and a newly-modified tunneling-induced ground settlement calculation method was presented.It is revealed that the maximum surface settlement decreases and the transverse settlement trough is widened with the increase of cover height,while the surface settlement increases with the augment of the face supporting pressure.The surface settlement is hardly influenced by the shield penetration,but obviously influenced by boundary soil disturbance induced by shield tunneling.
-
Key words:
- shield tunnel /
- physical model /
- ground surface settlement /
- experimental study
-
刘纪峰,陶龙光,刘波.考虑盾构施工扰动土体固结的地层沉降计算[J].辽宁工程技术大学学报:自然科学版,2009(5):731-734. [2] 孙钧.城市环境土工学[M].上海:上海科学技术出版社,2005. [3] 徐前卫,朱合华,廖少明,等.软土地层土压平衡盾构法施工的模型试验研究[J].岩土工程学报,2007,29(12):1849-1857. [4] 刘波,陶龙光,刘纪峰.隧道掘进试验用模拟盾构机:中国,200820140298[P].2009-09-09. [5] 郑宜枫,丁志诚,戴仕敏.超大直径盾构推进引起周围土体变形和土水压力变化分析[J].地下空间与工程学报,2006,12(8):1349-1353. [6] 裴红军,孙树林,吴绍明,等.隧道盾构法施工开挖面稳定性研究方法评析[J].地下空间与工程学报,2005,1(1):117-119. [7] Kasper T,Meschke G.A Numerical Study of the Effect of Soil andGrout Material Properties and Cover Depth in Shield Tunneling[J].Computers and Geotechnics,2006(33):234-247. [8] 刘纪峰,刘波,陶龙光.基于弹塑性分析的浅埋盾构隧道地表沉降控制[J].沈阳建筑大学学报:自然科学版,2009,25(1):28-33. [9] 叶康慨,王延民.土压平衡盾构施工土压力的确定[J].隧道建设,2003,5(2):47-51. [10] 张凤祥,朱合华,付德明.盾构隧道[M].北京:人民交通出版社,2004. [11] Celestino T B,Gomes R A M P,Bortolucci A A.Errors inGround Distortions Due to Settlement Trough Adjustment[J].Tunnelling and Underground Space Technology,2000,15(1):97-100.
点击查看大图
计量
- 文章访问数: 71
- HTML全文浏览量: 10
- PDF下载量: 103
- 被引次数: 0