RESEARCH ON THE KEY TECHNOLOGIES OF JINGHANG GRAND CANAL CONTINUOUS BEAM’S CONSTRUCTION MONITORING ON SHANGHAI-NANJING INTERCITY RAILWAY
-
摘要: 施工监控已被广泛应用于高速铁路大跨度桥梁建设中,以沪宁城际铁路京杭大运河(75+125+75)m预应力混凝土连续梁施工监控为例,介绍线形控制和应力监控方面的关键技术和适用方法,包括预拱度设置、挂篮变形确定、基于概率分析的变形预测、传感器数据分析、温度影响分析与控制技术等,对混凝土连续梁线形控制的主要环节进行了计算分析。经过施工实践证明:监控效果理想,监控成果表明监控方法的可靠性和适用性。Abstract: Construction monitoring has been widely used in long-span bridges construction of high-speed railway.Combining with the construction monitoring of Jinghang Grand Canal(75 + 125 + 75)m prestressed continuous beam,it is introduced some key technologies and application methods of the deformation control and stress control,including: setting of the camber,determination of the bailey truss deformation,deformation prediction based on probability analysis,stress analysis of sensor data,analysis of temperature effect and controlling method,etc.it is done a calculation of concrete continuous beam deformation control.It is proved by construction practice that the monitoring results are satisfactory,which show the reliability and applicability of this monitoring method,which also provides a reference for similar bridge construction.
-
[2] 李红涛.高墩大跨径桥梁施工中的结构及变形监控[J].甘肃科技纵横,2006,35(3):131-132. 段明德.大跨度预应力混凝土桥梁施工的线形控制[J].铁道建筑技术,1996 (6):1-5. [3] TB 10002.32005 铁路桥涵钢筋混凝土和预应力混凝土结构设计规范[S]. [4] 金福根.贝雷桁架挂篮仿真分析[J].科技创新导报,2008(3):255. [5] 盛超,于天来.箱梁桥悬臂浇筑施工中的温度效应及其控制[J].森林工程,2008,24(1):78-79. [6] 曾德荣,张增亚.桥梁施工监测应力误差计算方法[J].公路交通技术,2005(4):113-114. [7] 周履,陈永春.收缩徐变[M].北京:中国铁道出版社,1994.
点击查看大图
计量
- 文章访问数: 92
- HTML全文浏览量: 7
- PDF下载量: 91
- 被引次数: 0