FORCED PERFORMANCES STUDY ON TOTAL-PRECAST CONCRETE FRAME COLUMN WITH ALVEOUS-CONNECTION
-
摘要: 通过低周反复循环荷载试验,研究全预制齿槽连接框架柱的受力性能。结果表明:在同等条件下,全预制齿槽连接框架柱具有与整浇柱相当的受力性能;利用齿槽连接的全预制柱传力路径明确,可以在工程中加以应用。Abstract: The forced performances of total-precast concrete frame columns with alveous-connection were investigated under low reverse cyclic loading.The results showed that the forced performances of a total-precast concrete frame column with alveous-connection was equal to the cast-in-suit one.It was concluded that the load transfer path of total-precast concrete frame column with alveous-connection is definite,it could be applied in practice.
-
Key words:
- forced performances /
- alveous-connection /
- total-precast
-
[2] 薛伟辰.预制混凝土框架结构体系研究与应用进展[J].工业建筑,2002,32(11):47-50. Prestressed ConcreteInstitute. PCI DesignH and book[M].1978:5-51. [3] 唐九如.钢筋混凝土框架节点抗震[M].南京:东南大学出版社,1989:197-278. [4] 李湘洲.国外预制装配式建筑的现状[J].建筑科学,2004,16(6):24-27. [5] Fu F,LamD. Experimental StudyonSemi-Rigid Composite Jointswith Steel Beams and Precast Hollowcore Slabs.[J]. Journal of Constructional Steel Research,2006:771-782. [6] Zhu Zhenyu,A M ASCE,Iftekhar Ahmad,et al. Seismic Performance of Concrete-Filled FRP Tube Columns for Bridge Substructure[J]. Journal of Bridge Engineering,2006(5):359-370. [7] 赵斌,吕西林,刘海峰.预制高强混凝土结构后浇整体式梁柱组合件抗震性能试验研究[J].建筑结构学报,2004,25(6):22-28. [8] 柳炳康,张瑜中,晋哲锋,等.预压装配式预应力混凝土框架接合部抗震性能试验研究[J].建筑结构学报,2005,26(2):60-66. [9] 李忠献,张雪松,丁阳.装配整体式型钢混凝土框架节点抗震性能研究[J].建筑结构学报,2005,26(4):32-38.
点击查看大图
计量
- 文章访问数: 136
- HTML全文浏览量: 6
- PDF下载量: 44
- 被引次数: 0