APPLICATION OF THE MAST FULL HINGED SUSPENSION STRUCTURE IN JILIN SPEED SKATING RINK
-
摘要: 通过吉林省速滑馆的工程实践,总结桅杆式全铰接悬挂体系的特点,讨论考虑钢结构、钢索制作安装误差因素的全过程施工模拟分析,确定钢索零状态长度和可调节头调节长度,提出预应力空间结构预应力组合施加的概念,预应力多次张拉与组合施加通过计算分析进行过程控制的实施方法,并通过钢索索力监测进行验证。Abstract: Through the application of the cable-steel roof of Jilin Speed Skating Rink,the construction characteristics of the mast full hinged suspension structure were summarized;full simulative construction analysis process in which error factors of the steel structure and cable making and erection were taken into account fully was discussed;the conception and method carried out on prestressed spatial structure that prestress should be applied compositely was put forward.
-
Key words:
- mast /
- suspension structure /
- full hinged /
- nonlinear /
- error /
- prestress composite application
-
曾滨.大跨度全铰结悬挂结构应用研究课题研究报告[R].北京:中冶集团建筑研究总院,2007. [2] 董石麟.新型空间结构分析、设计和施工[M].北京:人民交通出版社,2006. [3] 陆赐麟.现代预应力钢结构[M].北京:人民交通出版社,2007. [4] CECS 212:2006预应力钢结构技术规程[S]. [5] 孙丹丹,丁洁民,何志军.张弦网壳结构的静力分析与施工过程优化分析[J].工业建筑,2008,38(6):86-91.
点击查看大图
计量
- 文章访问数: 76
- HTML全文浏览量: 7
- PDF下载量: 39
- 被引次数: 0