摘要: 探讨在超长混凝土结构的设计与施工中,由混凝土收缩及季节温差引起的结构内力的分析方法;收缩及季节温差间接作用的极限状态设计方法;收缩与温差引起的结构内力的异同;超长混凝土结构的分段流水施工问题;在超长混凝土结构中,如何合理配置预应力筋及非预应力筋等问题。Abstract: For design and construction of over-long concrete structures, some problems are discussed.These include analysis methods of structural internal force due to concrete shrinkage and difference in temperature, limit state design methods considering indirect action, similarities and differences of structural internal force due to concrete shrinkage and difference in temperature, segmental construction, rational se-t up of prestressing tendons and non-prestressed reinforcing bars etc.
-
Key words:
- over-long concrete /
- structure shrinkage temperature /
- stress design segmental /
- construction /
-
GB 50010-2002 混凝土结构设计规范 过镇海, 时旭东.钢筋混凝土原理和分析.北京: 清华大学出版社,2003: 13-14 王勖成.有限单元法.北京: 清华大学出版社, 2003: 302 -333, 王铁梦.工程结构裂缝控制.北京: 中国建筑工业出版社, 1997:2-23 韩重庆, 冯 健, 吕志涛.大面积混凝土梁板结构温度应力分析的徐变应力折减系数法.工程力学, 2003( 2): 7-14 吴 京, 武俊燕, 孟少平.混凝土结构间接应力及其裂缝控制研究.工业建筑, 2006, 36(5): 13-15 王春武, 孟少平.预应力混凝土框架结构的抗震设计探讨.工程抗震与加固改造, 2005( 5): 33-36 -616
点击查看大图
计量
- 文章访问数: 70
- HTML全文浏览量: 9
- PDF下载量: 46
- 被引次数: 0